Quantcast
Channel: Lebo Citizens
Viewing all articles
Browse latest Browse all 1248

Change orders for May 2014

$
0
0
The Agenda for the May 12, 2014 School Board Meeting has been published.

Change Orders for High School Renovation Project – The following change orders are presented for Board consideration. All the change orders listed below totaling $104,477 have been reviewed by the architect, PJ Dick and the District administration.

a. GC-100-225 to Nello for $74,520 for floor, wall, structure and ceiling work,

b. PL-30-226 to Vrabel for $16,793 for drain, water and storm lines and heater repairs,

c. EL-61-227 to Farfield for $873 for cable, fire alarm, card reader and gas resets, and

d. ME-23-228 to McKamish for $12,291 for diffusers, ducts and coils.


Viewing all articles
Browse latest Browse all 1248

Trending Articles