Change orders for the month of June:

5. Change Orders for High School Renovation Project – Change orders for Board Approval for the month of June total $265,923 with $258,927 allocated from the Contingency Budget and $10,118 from the Capital Project Budget as follows:

a. GC-101-229 to Nello for $95,000 for gym floor and scheduling changes,

b. GC-102-230 to Nello for $75,768 for building, wall, floor, door and structure revisions,

c. PL-31-231 to Vrabel for $20,849 for water line rerouting and garbage disposal connections,

d. EL-62-232 to Farfield for $32,909 for raceways, zone boxes, breakers, dampers and data connections,

e. ME-24-233 to McKamish for $31,279 for HVAC, vent, ductwork and fan changes, and

f. CW-03-234 to Reed for $10,118 for additional countertops funded from Capital Budget.



Word on the street is that the high school project will be completed Fall 2015. We'll see about that. We were promised that Hotel Tyvek was definitely opening July 1. That has been moved [again] to September 1.

Finally, I hear that the Rifle Range will be showing up shortly as a $500,000 capital project.